Westbrook Associated Engineers

Tomorrow's Engineering Solutions Today

  • Home
  • About Us
  • Leadership
  • News
  • Services
    • Bridge Design
    • Construction Engineering
    • Construction Administration
    • Frac Sand Consulting Services
    • Marine Engineering
    • Roadway Design
    • Survey
  • Careers
  • Contact Us

Chicago Harbor Lock Rehabilitation

June 24, 2022 By Mysti Nundahl

The Chicago Harbor Lock, near downtown Chicago, is the transition point between Lake Michigan and the Chicago River for a variety of commercial and recreational vessels. The lock allows vessels to transit from the Chicago River’s stable elevation to Lake Michigan’s fluctuating elevation with ease.

The Harbor Lock is undergoing a series of renovations to maintain and improve the current facilities. J.F. Brennan Company is working with the Army Corps of Engineers to construct repairs to the Lock walls and floor. Westbrook and J.F. Brennan have teamed up to creatively engineer a quick and cost efficient repair plan.

Chicago Harbor Lock As-Built 1936 Plans

The as-built plans for the Lock date back to 1936. The plans detailed Precast Concrete Panels to cover the floor of the lock. Over the 85+ years, these panels have shifted and settled unevenly presenting a hazard to high-draft boats and barges. Westbrook is using 3-D Contour Scans, and LIDAR Bathymetry data (provided by J.F. Brennan) in combination with the existing plans, to determine the extent of settlement, scour, and shifting that has occurred at the lock floor. From this data, we are assisting J.F. Brennan in creating an accurate means-and-methods plan to facilitate the repairs and partial replacement of the Chicago Harbor Lock floor. Anchored precast and cast-in-place elements will be incorporated into the design.

Chicago Harbor Lock
Bathymetry Scan
Contour Scans

Filed Under: News

I-74 River Bridge – Illinois Approach

June 21, 2022 By Mysti Nundahl

IowaDOT and IllinoisDOT built a new I-74 river bridge over the river at Moline, IL to Bettendorf, IA. Kraemer North America (KNA) was selected to build the Illinois approach and remove the existing bridge. KNA hired Westbrook to design the removal of the existing 26-span Steel Girder Structure, along with four curved steel ramps.

After an on-site inspection, Westbrook designed a complete removal plan for all of the concrete deck, and for all of the steel girder spans, including demolition sequencing, crane capacity checks, curved girder stability, and stability of remaining spans.

Westbrook was also able to accommodate BNSF Railroad traffic under span 15, and several adjustments in the schedule for traffic control, and construction sequencing.

We are happy to share that the project is complete and the new I-74 bridge is OPEN!

I-74 River Bridge
Photo from: Official Facebook page for the I-74 Mississippi River Bridge project, on behalf of Iowa DOT and IDOT
I-74 River Bridge
Photo from: Official Facebook page for the I-74 Mississippi River Bridge project, on behalf of Iowa DOT and IDOT

Filed Under: News

I-280 Bridge over Mississippi River

May 25, 2022 By Mysti Nundahl

Westbrook worked with Kraemer North America on the I-280 bridge over the Mississippi River at Rock Island, IL and Davenport, IA to analyze the existing 570′ tied arch span.  The existing deck was slated to be removed and replaced in two stages.  Westbrook analyzed various construction procedures and loading patterns for the deck removal to ensure that no existing arch members exceeded their design capacity.  The deck pour sequence was also re-designed to allow for a more efficient process to reduce construction time.

I-280 Bridge over Mississippi River at Rock Island, IL/Davenport, IA

 

 

 

 

 

This structure required a 3D analysis in STAADPro to check each member of the I-280 bridge for both wind and vertical loading from equipment and structure dead load changes as the old deck was removed and the new deck poured.  Shielding to enclose the painting added more surface area for wind.

3D analysis in STAADPro

Filed Under: News

Sandy Ford Girder Erection

May 17, 2022 By Mysti Nundahl

The Sandy Ford girder erection of the new single span 214’ structure over Vermillion River at Sandy Ford Nature Area in Lasalle County, IL presented numerous challenges including difficult site access, a limited permit for river work, and very long heavy girders.  To facilitate the construction of the structure, Westbrook designed a girder launching system to allow the girders to be constructed and braced together behind the abutment and “launched” into place.  Supply chain issues in a tight timeline prevented this plan from being implemented.

Westbrook put together an alternate girder erection design that required two cranes to pick and hold individual girder sections in place while they were air-spliced.  Then two additional cranes held this first girder in place until the second girder sections were set, air-spliced, and diaphragmed to the first girder.  Westbrook provided on-site inspection to ensure the Sandy Ford girder erection was performed per plan.

Girder Erection - County Highway 5 over Vermillion River at Sandy Ford Nature Area Lasalle County, IL

Filed Under: News

I-74 over Vermillion River – Danville, IL

May 12, 2022 By Mysti Nundahl

I-74 over Vermillion River - Danville, ILI-74 over Vermillion River in Danville, IL was an existing (2) girder fracture critical 750’ long structure built in 1962 and is being replaced with a redundant (6) girder steel plate girder structure, re-using the same substructure units.   Westbrook provided all aspects of the construction engineering.

Westbrook analyzed the existing I-74 over Vermillion River structure throughout removal operation stages. Existing superstructure removal was performed with an excavator on the structure removing concrete deck panels.  Steel girders were picked with a crane below the structure, on a Westbrook designed causeway and temporary bridge to maintain river flow.

The new structure girder erection and all aspects of the stability of the girders during construction was designed by Westbrook.  We also provided designs for the bridge deck falsework, falsework at the vaulted abutment span, and temporary work platforms.

Phase one can be seen within the photos attached and has been completed. Phase 2 is currently in motion; just recently the pier caps have been poured.

 

Filed Under: News

  • 1
  • 2
  • 3
  • …
  • 12
  • Next Page »

Latest News

  • Chicago Harbor Lock Rehabilitation
  • I-74 River Bridge – Illinois Approach
  • I-280 Bridge over Mississippi River
  • Sandy Ford Girder Erection

Connect With Us

  • Email
  • Facebook
  • LinkedIn

Westbrook Associated Engineers, Inc.
619 East Hoxie Street
Spring Green, WI 53588
Phone (608) 588-7866

Copyright © 2022 · Westbrook Associated Engineers, Inc · Spring Green, WI · Design by CDRC